To keep profits growing in these days of flat revenues, manufacturers
are paying more attention to the advice of Poor Richard (a.k.a. Benjamin
Franklin): A penny saved is a penny earned.
Those intimately involved in the quality improvement movement know those
pennies are to be found in reducing rework and scrap and creating a smooth
production flow.
We can all agree on reducing scrap and rework. The question is, by which
ideology? Six Sigma programs are popular, focused and effective, but projects
often take months to finish, and the program creates elite Black Belts
(BBs), who are frequently disconnected from the shop floor.
Lean initiatives are great for boosting productivity, changing a culture
and cleaning up factories, but what tools do they offer when it comes
to fixing unseen quality issues?
Companies from across the spectrum--making playground equipment, commercial
refrigeration units or washers and dryers--have found the most effective
way to eliminate the flaws that lead to rework and scrap, and create one
unified idea of continuous improvement, is by combining lean/kaizen
and Six Sigma.
The resulting one-two punch becomes a formidable tool for attacking
the problems that enlarge the difference between annual revenues and the
bottom line.
The two initiatives work together, achieving results consistently superior
to what either system could achieve alone. It's a classic case of the
whole being greater than the sum of the parts.
Lean brings action and intuition to the table. Based on the principals
of the Toyota Production System and kaizen (continual improvement)
breakthrough methodology, lean focuses on creating one-piece flow with
just-in-time management of inventory and materials. Using five-day kaizen
events, cross functional groups improve lead time and reduce inventory
on the spot, attacking the kind of quality and flow issues referred to
as "low hanging fruit."
Picking that fruit clears the branches, allowing you to clearly see
the kinds of challenges that require a Six Sigma approach using statistical
tools to uncover the unseen roots of problems.
Popularized by Motorola and General Electric, Six Sigma has been marketed
as a silver bullet, but the approach has a downside. By creating a cadre
of Master Black Belts (MBBs), who can spend six months or more on a single
project, the approach sacrifices the bias for action inherent in lean
projects. Momentum for transformation is lost.
By looking at projects through both the lean and Six Sigma lenses, you
have the precision, actionable tools needed to find hidden problems while
making sure you don't overlook the obvious.
Case Study
Consider the case of a prominent playground equipment manufacturer,
Landscape Structures Inc. in Delano, MN. The company had been working
on lean techniques for more than a year--cutting lead time in manufacturing
by 92%, improving productivity by more than 20% and dropping scrap from
0.8 to 0.2%--when it uncovered a problem that seemed to need more of a
Six Sigma style approach. Pinholes in PVC coated pipes were causing a
lot of scrap. The most likely culprits were the temperature, angle or
mill thickness at which PVC was being applied. Landscape Structures asked
TBM Consulting Group to help, using a method called LeanSigma that combines
lean, kaizen and Six Sigma.
We set out to understand what we were trying to fix by measuring all
the variables. A team made up of a cross-section of operators, engineers
and managers from Landscape led by a TMB consultant spent hours on the
shop floor observing, both to collect fresh data and to understand the
context. Like TV detective Columbo, you can uncover a lot of information
just by watching. You can get much closer to a problem if you catch it
in action, rather than just see historical data flash across a screen
in a PowerPoint presentation with illustrated charts.
We mapped the entire process. By learning which tubes were processed
on which rack at exactly what temperature, we could trace any defects
found at the end of the line back to the process responsible. A month
later, we scheduled a second event that would allow the same team to analyze,
improve and, ultimately, control the process and put improvements into
place.
Even though the company had been practicing lean for a year and a half,
we found many things that needed mistake proofing (poka-yoke).
For example, there was the priming system. Some parts got primed, some
did not, but all the parts were manually placed on a rack system before
the primer bath.
The operator had to know which racks needed to be primed, and some operators
were more knowledgeable about this part of the job than were others. Sometimes
parts that needed primer did not get it and vice versa.
The company created a standard operating procedure showing which parts
should be primed, and put in an electric signal--a poka-yoke--to
indicate which rack should be dunked into the primer bath.
The idea was to take the variability out in order to assess what was
going on in the core process. Once we were able to do that, we could determine
the problem was not related to PVC at all. So, we started moving back
the line to look for potential causes of the problem.
We found it in welding. We started all over again, measuring and mapping
in that department. We discovered there were no standard settings for
welders, with every employee having a different idea of what a "good flame"
was. Once we created a standard operating procedure and gave new training
to the welders, the pinhole problem was solved.
Combining Six Sigma and lean techniques allowed us to discover where
the problem wasn't, an important step toward ultimately finding where
it was.
Often, we are preconditioned by notions of what has happened in the
past. History becomes baggage we bring to solving immediate problems,
causing us to blame the wrong culprit--in this case the PVC application
process. The precise measuring demanded by Six Sigma gets us past preconceived
notions to tracking the real problem, which can turn out to be quite simple.
We all tend to believe problems are far more complicated than they actually
are, simply because they have yet to be solved. The sense of urgency inherent
in lean keeps us from dragging out a problem and adding complexity.
A Second Case Study
Sometimes the real problem can be solved best with lean techniques;
other times Six Sigma is at the heart of the solution.
That was the case at Heatcraft, a Georgia factory that makes commercial
refrigeration equipment. The factory had been using lean for a year to
improve production. Still, too many of the units were coming off the line
leaking, creating costly rework loops, warranty claims and customer dissatisfaction.
The plant tests units by submerging them in water and running air through
the coils while the operator looks for bubbles. Where there are bubbles,
a leak has been found. Sometimes, when a coil is retested after rework,
new leaks appear from holes too small to be noticed until the bigger leaks
are repaired. That means more rework.
The first step was to determine the major causes of leaks. Analysis
revealed more than half the leak problems were in the return bend of the
coils, the hundreds of narrow copper tubes the refrigerant passes through
to cool off the heat it has absorbed from the air inside a plant. To make
the coils, lengths of tubing are cut and connected with a U-shaped return
bend.
Where the return bend meets the tube, the connection is brazed (a precision
cousin to soldering). A brazed joint has a pocket where one tube meets
the other. A liquid at just above melting temperature is injected into
the pocket, filling it to create a neat joint.
Based on a Pareto analysis, a LeanSigma team led by Doug Bonner, a TMB
senior consultant and Six Sigma BB, found 50% of all leaks were springing
from the return bend joint and set a goal of reducing the leaks from return
bends by 75%.
"Once we knew what to work on, we began to map out the process," said
Bonner. The team started its first kaizen event by breaking down
the transformation steps, noting each time the product changed state.
For example, cutting a piece of tube was one transformation step, and
installing it was another. In all, the team found at least 20 transformation
steps and collected data at each to find possible sources of variation
in the braze process.
The team found dozens of variations in the way the units were made,
from how far the coils were from each other to how much the tubes stuck
out before brazing connected them to the return bend. The torch temperatures
were actually very consistent, unlike the situation at Landscape Structures,
so that possible cause was ruled out.
Actionable items were marked: red stars for control issues and green
stars for measurement issues. "There was a lack of control in the process,"
said Bonner. "We needed stability."
The map created in the first week became a core document that drove
the team's focus. One important clue found in the mapping was that the
plant made two types of units with the same bend design. They showed drastically
different leak rates. Maybe one line could learn from the other.
Team members also created a cause and effect diagram for the process,
listing the "five M's and E": materials, methods, machinery, measurement,
manpower and environment. Flaws in any step could be causing the problem.
"All you need is one defect to cause a lot of grief," Bonner said. Each
step had to be carefully measured and, more importantly, its effect on
the final product examined more closely.
The team drew plots for each M, similar to trees, with a trunk, main
branches and smaller branches. For example, on the machine trunk, one
branch was "torch tip bent wrong." That branch split off into "hole in
joint" and "improper mix" of fluids. "Incorrect brazing" branched off
into a half-dozen effects. In other words, one problem led to another.
A fishbone diagram, derived from the
preceding, is shown in Figure
1.
In an application of a lean procedure in the midst of this combination
lean and Six Sigma exercise, the team also noted operators were not receiving
any feedback on joint quality from their co-workers at the test tank.
They had no way to know whether their work was high quality or needed
improvement.
The lean Six Sigma team corrected that oversight immediately by having
each brazer stop to fix quality issues on parts he or she had brazed,
resulting in better quality at the source.
The next challenge was to determine which of the variations contributed
to leakage. That required analysis, particularly of differences between
the two lines.
The team determined whether leaks were coming from the same place on
the coil or the same location on the braze joint. Intuitively, the team
suspected the problem was with tubes that did not stick out far enough.
Team members followed the process through on the shop floor and found
that when the tubes were longer with more overlap, there was, in fact,
better coverage.
The team learned the joints with greater distance from the end plate
were consistently better and those with less overlap between the coil
tube and the return bend had a higher percentage of braze material coverage.
The efforts from that first Six Sigma kaizen week yielded a 75%
reduction in quality issues and a 40% overall reduction in leak rates.
The team accomplished this by focusing on just one defect. But there
were ancillary benefits, too. The team's efforts and observations also
corrected problems with the header--a sort of manifold that stands about
4 inches off the unit. After watching and mapping the process, the team
discovered the piece was not being seated properly in the joint. Moving
it out 1/4 inch and instituting a standard specification solved the problem.
The improvements led to a significant reduction in defects and better
flow and throughput.
The results justified the hard work of the kaizen team: hours
observing and measuring, one day mapping and several days collecting data
on each process. Improvements were achieved by combining the best of lean
and Six Sigma and making them work together.
The Role of Leadership
In looking at lean and Six Sigma, too many manufacturing companies believe
they have to choose one approach to the exclusion of the other. Those
that try both often find they compete for resources or, worse, foster
a culture clash.
That clash might seem unavoidable. After all, lean programs center on
teamwork and breakthrough events. Six Sigma tends to develop an aristocracy
of quality engineers who spend months collecting data and punching it
into computers, far from the daily work of the shop floor.
When run separately, such programs will naturally collide with each
other. In contrast, a combination of lean and Six Sigma has a positive
impact on employee morale, inspiring change in the workplace culture because
teams see the results of their efforts put to work almost immediately.
For that positive change to take place, however, management must believe
in it. First, executives must develop the vision and deployment strategy
to make this powerful initiative work. In TBM's five-day LeanSigma Champion
training program, executives assess their current practices and define
the business objectives of the combination lean and Six Sigma initiative.
Champion training requires time and commitment, but if top level management
does not spend time on this cultural change, no one else will, either.
"Do as I say and not as I do" will not work.
During Champion training, executives also handpick the first group of
BBs, assuring the first projects will have enthusiastic, educated leaders
who will get support from both above and below.
In the combination lean and Six Sigma world, BBs are change agents.
They receive four weeks of training that culminate in a project demonstrating
a substantial financial benefit to the company. BBs lead teams, urge action
and ensure all improvements become cemented in the standard operating
procedures.
Green Belts (GBs) can be engineers, supervisors, quality control experts
or operators. They train half as long and then participate in projects
without leaving other responsibilities. In the combination, GBs rely on
BBs for mentoring.
Just as important to real, long-term change are the softer issues infused
in lean combined with Six Sigma. Improvement must be implemented without
placing blame on individuals for the way things used to be done. People
cannot understand what they are supposed to be doing unless processes
are in place. Besides, from a practical standpoint, you usually uncover
so many separate issues that management, working in a culture of blame,
would have to fire the whole company.
Instead, the idea is to implement a culture of continuous improvement.
Using the Six Sigma kaizen team based approach, results are implemented
faster with the participation of teams of employees from the shop floor
to the executive suite. Most people prefer to work in that sort of environment.
Link to Employee Satisfaction
Vermeer, a farm and construction equipment manufacturing company in
Iowa, found employee satisfaction directly related to participation in
kaizen events. The company's COO participates in several events
a year, showing her commitment.
A survey conducted by an outside agency found employees who had participated
in more than six events are 20% more favorable toward the company than
those who had not participated.1 Those who had not participated in any kaizen events
felt more negative about the company. There is a direct correlation.
Workers feel proud of making better products at the same time they improve
their working conditions. Change can be exhilarating--and profitable.
A fusion of two proven practices, lean and Six Sigma, can facilitate that
outcome.
REFERENCE
1. International Survey Research, Chicago, 2000.
BONNIE SMITH is director of LeanSigma quality improvement
for Durham, NC, based TBM Consulting Group Inc., the sole licensee of
Maytag Corp.'s Lean Sigma service mark. She earned a bachelor's degree
in mechanical engineering from the United States Military Academy. Smith
is also a Six Sigma Master Black Belt.